Lighthouse Apartments Construction Update

A lot has changed since our last update on Lighthouse, an SJB-designed apartment project situated on the edge of Australia’s largest marina, Wyndham Harbour. Construction is progressing on schedule with 75% of level 3 slabs now poured. It is anticipated that level 3 & 4 slabs and roof framing will be completed by the end of June in preparation for winter.

Windows and doors have also been manufactured with the first batch already completed and ready for delivery on site in the next month. Ground floor concrete form works removal has also commenced to allow for the installation of the internal wall frames. 

We’re looking forward to seeing the final product, with construction slated for an early 2018 completion.