Significant progress has been made, with joinery and stone installation, along with the installation of kitchen hardware, completed in our most advanced blocks.
Work in the northern parkland area is in progress and is expected to be finished by mid-December, encompassing lawn and planting tasks.
Preparations for roads, crossovers, and the public external areas are underway and scheduled for completion by early December.
The external façade and cladding work is nearing completion for the entire project.
The first set of blocks is on track to be finished by mid-December, marking a key milestone in the construction timeline.