Construction Update | Immerse

Construction at Immerse is well underway with Merkon progressing rapidly on-site.

Internally on levels one, two and three, waterproofing and initial paint coats have been completed. On the higher levels, levels four and five, plaster works have commenced along with the completion of the ceiling grid.

Externally, render works have been initiated to the west elevation of the building and the façade arches. With the tower crane now dismantled, and the lift lid installed, the building façade screens have commenced installation.